Feasibility

Understand what's possible

  • Identify the right location on your lot
  • Site assessment for required utilities and site preparation
Feasibility
Hi Jess, We’ve done a survey of your property and determined where you’re able to build and where we’ll tie into utilities.
We estimate this would work within your budget of $200k - $225k.
avatar
2
2
Design
2-6 weeks

Design your custom ADU

  • Develop your floor plan
  • Select your finishes
  • Visualize your plans in 3D
Explore Floor Plans
Design
3
3
Permitting
10-16 weeks

Relax as we handle permitting

  • Full architectural sets for swift city permitting
  • Fully managed site surveying & engineering
  • Track progress via our online Portal
Permitting
Hey Jess, your permit application has been submitted.
It should take 2-4 weeks for the city to review and respond. Contact me anytime if you have questions.
avatar
4
4
Construction
12-16 weeks

Build with trusted pros

  • Your builder handles everything from site prep to final inspection
  • Managed procurement process
  • Track invoices & make payments online
ConstructionConstruction